- Hardware overview
- Supported software
- 5340 compute node and 5U84 storage shelves
- 5340 compute node and storage shelf power requirements
- 5340 compute node disk drives
- 5340 compute node control panel
- 5340 compute node rear panel
- 5U84 storage shelf drawers and disk drives
- 5U84 storage shelf control panel
- 5U84 storage shelf rear panel
- 5U84 storage shelf RAID controller
- 5U84 storage shelf Expansion module
- Cables and connectors
- Preinstallation requirements
- Hardware installation procedures
- Overview
- Installing a storage shelf
- Installing disk drives into a full-capacity storage shelf
- Installing disk drives and blanks into a half-capacity storage shelf
- Installing SFPs into the RAID controller
- Installing the compute node rack rails
- Installing the compute node into a rack
- Connecting the hardware to one node
- Connecting the hardware to two nodes
- Connecting NetBackup nodes to the network
- Connecting Flex nodes to the network
- Connecting the power cords to the hardware
- Turning on the hardware and verifying operation
- Configuring the IPMI port from the NetBackup Appliance Shell Menu
- Accessing and using the Veritas Remote Management interface
- Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
- Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
- Overview
- Turning off the existing hardware
- Installation instructions
- Connecting one Expansion shelf to a system that has one existing Expansion shelf
- Connecting two Expansion shelves to a system that has one existing Expansion shelf
- Connecting one Expansion shelf to a system that has two existing Expansion shelves
- Appendix C. Configuring the disk space for new NetBackup Expansion Storage Shelves
- Appendix D. Configuring the disk space for new Flex Expansion Storage Shelves
Best practices for rack installation
Prepare for the hardware installation by following these recommendations.
The storage shelves are heavier than the compute node and should be installed as close to the bottom of the rack as possible.
Determine device order and cabling limits.
Install one set of rails. Then install the device. Do not install all of the rails at one time as you may not leave enough room for the devices.
Be aware of the depth of the rails and the devices. Ensure that the distance between cabinet posts accommodates the rails, devices, cables, extending ears, and PDU strips.
Hold a 1m SAS3 cable between the intended locations for the Primary Storage Shelf and the last Expansion Storage Shelf. Visually confirm that the cable is long enough.