Please enter search query.
Search <book_title>...
Veritas NetBackup™ 5330 Appliance Hardware Installation Guide
Last Published:
2018-09-21
Product(s):
Appliances (Version Not Specified)
Platform: 5330
- Hardware overview
- NetBackup 5330 compute node overview
- NetBackup 5330 compute node PCIe card configurations
- NetBackup 5330 compute node Ethernet port configurations
- NetBackup 5330 storage shelves and disk drives
- NetBackup 5330 cables and connectors
- Serial number locations
- Required reading
- Understanding hardware scenarios
- Understanding the NetBackup 5330 hardware installation sequence
- About IPMI configuration
- Other NetBackup 5330 product documentation
- Pre-installation requirements
- Hardware installation procedures
- Hardware installation scenarios
- Installing a primary shelf or an expansion shelf
- Installing disk drives into a primary shelf or an expansion shelf
- Installing the compute node
- Installing the SFPs into the Fibre Channel (FC) ports
- Connecting a NetBackup 5330 compute node to a primary shelf
- Connecting one expansion shelf to a primary shelf
- Performing a soft shutdown before adding a new expansion shelf
- Connecting new expansion shelves to existing expansion shelves and an existing primary shelf
- Connecting the power cords to the hardware
- Turning on the hardware and verifying operation
- Configuring the IPMI port from the NetBackup Appliance Shell Menu
- Accessing and using the Veritas Remote Management interface
- Hardware installation procedures for a NetBackup 5330 high availability configuration
- Appendix A. Adding the disk space of a new Expansion Storage Shelf
Unpacking a primary shelf or an expansion shelf
Each storage shelf is shipped in a separate container. Veritas recommends that you have a table nearby where you can safely place the contents of the container.
Due to weight considerations the storage shelves ship without any disk drives installed.
Warning:
To unpack a storage shelf
- DO NOT slice open the top of the cardboard container.
- Remove the white, plastic inserts from the sides of the container.
- Lift up the top of the container.
- Lower and flatten the sides of the container so that you can access the storage shelf.
- Remove the front and the rear rack templates from the shipping container. You will use these templates to locate holes in the rack where screws and pins are placed.
Note:
The templates may be enclosed in the Open Me First box.
- Remove any foam, air bags, or other cushioning materials.
- Remove the extension bracket and screws.
- Remove the bezel and set it aside.
- Remove the mounting rails and set them aside.
- Remove the four metal handles and set them aside.
- Remove any fasteners, power cords, and cables and set them aside.
- Remove the storage shelf from the shipping container.