  1. Hardware overview
    1.  
      NetBackup 5330 compute node overview
    2.  
      NetBackup 5330 compute node PCIe card configurations
    3.  
      NetBackup 5330 compute node Ethernet port configurations
    4.  
      NetBackup 5330 storage shelves and disk drives
    5.  
      NetBackup 5330 cables and connectors
    6.  
      Serial number locations
    7.  
      Required reading
    8.  
      Understanding hardware scenarios
    9.  
      Understanding the NetBackup 5330 hardware installation sequence
    10.  
      About IPMI configuration
    11.  
      Other NetBackup 5330 product documentation
  2. Pre-installation requirements
    1.  
      Package contents for NetBackup 5330 hardware
    2.  
      Customer-provided items for a NetBackup 5330 hardware installation
    3.  
      Unpacking a primary shelf or an expansion shelf
    4.  
      Unpacking a compute node
    5.  
      Determining rack locations
    6.  
      Determining SAS2 cable length
    7.  
      Prerequisites for IPMI configuration on a 52xx and 5330
  3. Hardware installation procedures
    1.  
      Hardware installation scenarios
    2.  
      Installing a primary shelf or an expansion shelf
    3.  
      Installing disk drives into a primary shelf or an expansion shelf
    4.  
      Installing the compute node
    5.  
      Installing the SFPs into the Fibre Channel (FC) ports
    6.  
      Connecting a NetBackup 5330 compute node to a primary shelf
    7.  
      Connecting one expansion shelf to a primary shelf
    8.  
      Performing a soft shutdown before adding a new expansion shelf
    9.  
      Connecting new expansion shelves to existing expansion shelves and an existing primary shelf
    10.  
      Connecting the power cords to the hardware
    11.  
      Turning on the hardware and verifying operation
    12.  
      Configuring the IPMI port from the NetBackup Appliance Shell Menu
    13.  
      Accessing and using the Veritas Remote Management interface
  4. Hardware installation procedures for a NetBackup 5330 high availability configuration
    1. Hardware installation scenarios for a NetBackup 5330 high availability configuration
      1.  
        Installation procedures for a new deployment of a high availability configuration
      2.  
        Installation procedures for converting existing systems to a high availability configuration
    2.  
      Connecting the partner node to the Primary Storage Shelf
    3.  
      Connecting two nodes for HA communication
    4.  
      Verifying the hardware installation of a high availability configuration
  5. Appendix A. Adding the disk space of a new Expansion Storage Shelf
    1.  
      Prerequisites for adding the disk space of new expansion shelves
    2.  
      Adding the disk space of an Expansion Storage Shelf from the NetBackup Appliance Web Console
    3.  
      Adding the disk space of an Expansion Storage Shelf from the NetBackup Appliance Shell Menu

Unpacking a compute node

Each node is shipped in a separate container from the storage shelves. Both types of devices are shrink-wrapped together. Veritas recommends that you have a table nearby where you can safely place the contents of the containers.

Warning:

The nodes weigh 30kg (66 lbs) each. Be sure that you have adequate personnel or a mechanical lift to move the node.

To unpack the node

  1. Open the cardboard container.
  2. Remove the Open Me First box and the poster at the top of the container.
  3. Remove the rail template from the Open Me First box.

    The template shows where the left-hand rail and the right-hand rail fit into the front and the rear of the rack.

    Fold the template at the yellow horizontal lines. There are two lines; one in the middle and one at the bottom of the template. Then you can align the rack holes in the template to the rack holes in your equipment rack.

  4. Remove the bezel.
  5. Remove the mounting rails.
  6. Remove the accessory box that contains the fasteners, the power cords, and other contents.
  7. Remove the node from the shipping container.