Veritas NetBackup™ 5330 Appliance Hardware Installation Guide
- Hardware overview
- Pre-installation requirements
- Hardware installation procedures
- Hardware installation procedures for a NetBackup 5330 high availability configuration
- Appendix A. Adding the disk space of a new Expansion Storage Shelf
Installation procedures for a new deployment of a high availability configuration
The installation procedures for a new deployment of a NetBackup 5330 high availability (HA) configuration are as follows:
Install the components from the bottom of the rack in the following order: the Expansion Storage Shelves, the Primary Storage Shelf, and then the two nodes.
For the installation instructions:
Connect the Expansion Storage shelves to the Primary Storage Shelf.
Connect one of the nodes to the Primary Storage Shelf.
See Connecting a NetBackup 5330 compute node to a primary shelf.
Connect the other node to the Primary Storage Shelf.
See Connecting the partner node to the Primary Storage Shelf.
Connect the two nodes for HA communication.
Verify the hardware installation of an HA configuration.
See Verifying the hardware installation of a high availability configuration.
Connect the power cords to the hardware.
Turn on the power to each component in the same order as the installation.