NetBackup™ Access 3360 Appliance Hardware Installation Guide
- Overview
- About the Veritas Access 3360 Appliance
- Supported software
- Access 3360 compute node and 5U84 storage shelves
- Access 3360 compute node disk drives
- About the compute node control panel
- Access 3360 compute node rear panel
- 5U84 storage shelf drawers and disk drives
- 5U84 storage shelf control panel
- 5U84 storage shelf rear panel
- 5U84 storage shelf RAID controller
- 5U84 storage shelf Expansion module
- Cables and connectors
- About IPMI configuration
- Pre-installation requirements
- Hardware installation procedures
- Overview
- Installing a storage shelf
- Installing disk drives into a storage shelf
- Installing the storage shelf bezels
- Installing the compute node rack rails
- Installing the compute node into a rack
- Connecting the hardware to one compute node
- Connecting the hardware to two compute nodes
- Connecting Access nodes to the network
- Connecting the power cords to the hardware
- Turning on the hardware and verifying operation
- Configuring the IPMI port
- Accessing and using the Veritas Remote Management interface
- Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
- Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
- Overview
- Turning off the existing hardware
- Installing the hardware
- Connecting one Expansion shelf to a system that has one existing Expansion shelf
- Connecting two Expansion shelves to a system that has one existing Expansion shelf
- Connecting one Expansion shelf to a system that has two existing Expansion shelves
- Appendix C. Configuring the disk space after adding one or more new Expansion Storage Shelves
Connecting two Expansion shelves to the Primary shelf
Both Expansion Shelves connect to the Primary Shelf but not directly to the compute nodes.
Note:
To connect two Expansion shelves to the Primary Shelf
- Verify that all compute nodes and the Primary Shelf are off and that the power cords are unplugged.
Do not remove the cables between the compute nodes and the Primary shelf.
- Obtain the two SAS3 cables that ship with each Expansion Shelf.
- Identify the single SAS-3 port on the right side of each controller module in the Primary Shelf.
- Identify ports A and C in each I/O module in the Expansion Shelf. Port B is not available for use.
- Connect the cables as follows:
Connect one cable to each of the SAS-3 ports on the right of each controller module on the Primary Shelf.
Connect the left cable from the Primary shelf to port A in the left I/O module on the closest Expansion shelf.
Connect the right cable from the Primary shelf to port A in the right I/O module in the farthest Expansion shelf.
Connect one end of a new cable to port C in the left I/O module of the first Expansion shelf.
Connect the other end of the cable to port A in the left I/O module of the second Expansion shelf.
Connect one end of the final cable to port A on the right I/O module of the first Expansion shelf.
Connect the other end of that cable to port C in the right I/O module of the second Expansion shelf.
- Verify the final cable configuration.
The following figure shows the cabling diagram for a two-node configuration:
The following figure shows the cabling diagram for a single-node configuration:
- Connect the power cords of all devices as described in this section.
- Turn on the devices in the proper sequence as described in this section.
- Add the new disk space as described this section.
See Adding the disk space of an Expansion Storage Shelf from the Access Appliance shell menu.