Veritas Access 3340 Appliance Hardware Installation Guide

Last Published:
Product(s): Appliances (8.4, 8.3, 8.2, 8.1, 8.0, 7.4.3, 7.4.2, 7.3.2)
Platform: Veritas 3340
  1. Overview
    1.  
      Supported software
    2.  
      Access 3340 compute node and 5U84 storage shelves
    3.  
      Access 3340 compute node disk drives
    4.  
      Access 3340 compute node control panel
    5.  
      Access 3340 compute node rear panel
    6.  
      5U84 storage shelf drawers and disk drives
    7.  
      5U84 storage shelf control panel
    8.  
      5U84 storage shelf rear panel
    9.  
      5U84 storage shelf RAID controller
    10.  
      5U84 storage shelf Expansion module
    11.  
      Cables and connectors
  2. Pre-installation requirements
    1.  
      Customer-provided environment and supplies
    2.  
      Storage shelf shipping container contents
    3.  
      Compute node shipping container contents
    4.  
      Dimensions and determining rack locations
    5.  
      Best practices for rack installation
    6.  
      Heat dissipation guidelines
    7.  
      Cable length verification
    8.  
      Prerequisites for IPMI configuration
  3. Hardware installation procedures
    1.  
      Overview
    2.  
      Installing a storage shelf
    3.  
      Installing disk drives into a storage shelf
    4.  
      Installing the storage shelf bezels
    5.  
      Installing the compute node rack rails
    6.  
      Installing the compute node into a rack
    7.  
      Connecting the hardware
    8.  
      Connecting Access nodes to the network
    9.  
      Connecting the power cords to the hardware
    10.  
      Turning on the hardware and verifying operation
    11.  
      Configuring the IPMI port from the Access Appliance shell menu
    12.  
      Accessing and using the Veritas Remote Management interface
  4. Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
    1.  
      Turning off the existing hardware
    2.  
      Installing the hardware
    3.  
      Connecting one Expansion shelf to the Primary shelf
    4.  
      Connecting two Expansion shelves to the Primary shelf
    5.  
      Connecting three Expansion shelves to the Primary shelf
  5. Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
    1.  
      Turning off the existing hardware
    2.  
      Installing the hardware
    3.  
      Connecting one Expansion shelf to a system that has one existing Expansion shelf
    4.  
      Connecting two Expansion shelves to a system that has one existing Expansion shelf
    5.  
      Connecting one Expansion shelf to a system that has two existing Expansion shelves
  6. Appendix C. Configuring the disk space after adding one or more new Expansion Storage Shelves
    1.  
      Adding the disk space of an Expansion Storage Shelf from the Access Appliance shell menu

Installing the storage shelf bezels

Each of the two drawers in a 5U84 storage shelf has a bezel which needs to be installed.

To install storage shelf bezels

  1. Be sure that both of the drawers are firmly and evenly installed into the shelf.
  2. Locate the two bezels that ship with each storage shelf.

    Each shelf has two different bezels. The top drawer bezel has an oval Veritas logo. The bottom drawer has a horizontal red line without a logo.

  3. As you stand in front of a storage shelf drawer place the bezel against the right side of the drawer.
  4. Align the posts on the rear of the bezel with the holes in the front of the drawer.
  5. Angle the left side of the bezel over the left side of the drawer.
  6. Press the bezel into the four holes in the drawer.
  7. Use a 2mm Hex screwdriver to secure the bezels with the four screws for each drawer.
  8. Use a screwdriver with a Torx T-20 bit to lock the drawers.