Veritas NetBackup™ Appliance Upgrade Guide
Upgrade time estimation
Use the following information to estimate the approximate time to complete an appliance upgrade.
Table: Upgrade scenarios and related time estimations
Model | Upgrade path | Estimated base time | Additional time considerations |
---|---|---|---|
5230 | 2.7.x -> 3.1.2 3.0 -> 3.1.2 3.1 -> 3.1.2 3.1.1-> 3.1.2 | 2.5 - 3 hours |
|
5330 | 2.7.x -> 3.1.2 3.0 -> 3.1.2 3.1 -> 3.1.2 3.1.1-> 3.1.2 | 2.5 - 3 hours | For appliances with Expansion Storage Shelf units, add 15 minutes for each unit. |
5240 | 2.7.3 -> 3.1.2 3.0 -> 3.1.2 3.1 -> 3.1.2 3.1.1-> 3.1.2 | 2 - 2.5 hours | N/A |
5340 | 3.1 -> 3.1.2 3.1.1-> 3.1.2 | 2 - 2.5 hours | N/A |
For all upgrade scenarios, add the necessary time to the estimates as follows:
Add 10 minutes for every 350,000 jobs on the master server. For example, add 30 minutes to a master server with a job list containing 1 million records.
Add 5 minutes for every 250 VLANs that you have configured.