VCS 5.0MP1_SOLARIS10: GAB: Port h halting system due to client process failure.

Problem

VCS 5.0MP1_SOLARIS10: GAB: Port h halting system due to client process failure.

Error Message

STACK of had's Kernel thread that hang the system

-----------------------------------------------------------------

genunix:cv_wait+0x38()
genunix:holdlwps+0xbc()
genunix:cfork+0x40()
unix:syscall_trap32+0xcc()

 

Solution

It's a know issue. Please see the Technote 57527. It's recommended to upgrade VCS 5.0MP1 to VCS 5.0MP3. Please refer to its Release Notes.